Title: Wiseman Storm Drainage Improvement Project Construction Change Order #1
Attachments: 1. Location Map - Wiseman Storm Drainage Improvement Project Construction Change Order 1

Title

Wiseman Storm Drainage Improvement Project Construction Change Order #1

 

Action

Action:

Approve change order #1 for $265,399.52 to Hall Contracting Corporation for the Wiseman Storm Drainage Improvement Project.

 

Body

Staff Resource(s):

Gina Shell, Engineering and Property Management

Susan Tolan, Engineering and Property Management

John Keene, Engineering and Property Management

 

Explanation

§                     The Wiseman Storm Drainage Improvement project includes installation of over 3,700 feet of storm drainage infrastructure and approximately 1,000 feet of bank stabilization and channel improvements.

§                     During construction, private utility companies revised the utility plans delaying the scheduling of relocations. Change Order #1 will provide funds to accommodate these delays including:

-                     Demobilization and remobilization, and

-                     Maintenance of the site during the delay including traffic control, erosion control and tree protection measures for the extended contract duration. 

§                     The new total value of the contract including change order #1 is $4,679,667 and funding is available within the project budget.

§                     The project is scheduled to be complete by third quarter 2017.

 

Charlotte Business INClusion