Title
Wiseman Storm Drainage Improvement Project Construction Change Order #1
Action
Action:
Approve change order #1 for $265,399.52 to Hall Contracting Corporation for the Wiseman Storm Drainage Improvement Project.
Body
Staff Resource(s):
Gina Shell, Engineering and Property Management
Susan Tolan, Engineering and Property Management
John Keene, Engineering and Property Management
Explanation
§ The Wiseman Storm Drainage Improvement project includes installation of over 3,700 feet of storm drainage infrastructure and approximately 1,000 feet of bank stabilization and channel improvements.
§ During construction, private utility companies revised the utility plans delaying the scheduling of relocations. Change Order #1 will provide funds to accommodate these delays including:
- Demobilization and remobilization, and
- Maintenance of the site during the delay including traffic control, erosion control and tree protection measures for the extended contract duration.
§ The new total value of the contract including change order #1 is $4,679,667 and funding is available within the project budget.
§ The project is scheduled to be complete by third quarter 2017.
Charlotte Business INClusion
Additional work will be performed by Hall Contracting Corporation and their existing subcontractors (Part D: Section 6 of the Charlotte Business INClusion Policy).
Fiscal Note
Funding: Storm Water Community Investment Plan