Title
Pennwood/Amado Storm Drainage Improvement Project
Action
Action:
A. Approve a contract in the amount of $1,107,570.20 to the lowest responsive bidder GreenWater Development, Inc. (SBE) for the Pennwood/Amado Storm Drainage Improvement Project, and
B. Authorize the City Manager to amend the contract consistent with the purpose for which the contract was approved.
Body
Staff Resource(s):
Angela Charles, Charlotte Water
Mike Davis, Storm Water Services
Logan Oliver, Storm Water Services
Explanation
§ This project will reduce flooding and replace aging infrastructure across Amado Street and along Pennwood Lane from Waterwood Street to the end of the cul-de-sac in Council District 1.
§ The work includes grading, storm drainage, water, sanitary sewer, curb and gutter, driveways, and asphalt grading.
§ On August 5, 2025, the city issued an Invitation to Bid; eight bids were received.
§ GreenWater Development, Inc. was selected as the lowest responsive, responsible bidder.
§ The project is anticipated to be complete by the first quarter of 2027.
Charlotte Business INClusion
GreenWater Development, Inc. is a city SBE.
Established MBE Goal: 7.00%
Committed MBE Goal: 9.56%
GreenWater Development, Inc. exceeded the established contract goal and has committed 9.56% ($105,909) of the total contract amount to the following certified firm(s):
§ Redstone Materials, Inc. (MBE, SBE) ($55,400) (hauling)
§ RRC Concrete, Inc. (MBE) ($50,509) (concrete)
Established WBE Goal: 4.00%
Committed WBE Goal: 7.56%
GreenWater Development, Inc. exceeded established contract goal and has committed 7.56% ($83,700) of the total contract amount to the following certified firm(s):
§ On Time Construction, Inc. (WBE, SBE) ($83,700) (masonry)
Fiscal Note
Funding: Stormwater Capital Investment Plan
Attachments
Attachment(s)
Map