Skip to main content
City of Charlotte Banner
File #: 15-24807    Version: 1 Name:
Type: Consent Item Status: Approved
File created: 8/18/2025 In control: City Council Business Meeting
On agenda: 9/22/2025 Final action: 9/22/2025
Title: Pennwood/Amado Storm Drainage Improvement Project
Attachments: 1. Map - Pennwood/Amado SDIP

Title

Pennwood/Amado Storm Drainage Improvement Project

 

Action

Action                     

A.                     Approve a contract in the amount of $1,107,570.20 to the lowest responsive bidder GreenWater Development, Inc. (SBE) for the Pennwood/Amado Storm Drainage Improvement Project, and

 

B.                     Authorize the City Manager to amend the contract consistent with the purpose for which the contract was approved.

 

Body

Staff Resource(s):

Angela Charles, Charlotte Water

Mike Davis, Storm Water Services

Logan Oliver, Storm Water Services

 

Explanation

§                     This project will reduce flooding and replace aging infrastructure across Amado Street and along Pennwood Lane from Waterwood Street to the end of the cul-de-sac in Council District 1.

§                     The work includes grading, storm drainage, water, sanitary sewer, curb and gutter, driveways, and asphalt grading.

§                     On August 5, 2025, the city issued an Invitation to Bid; eight bids were received.

§                     GreenWater Development, Inc. was selected as the lowest responsive, responsible bidder.

§                     The project is anticipated to be complete by the first quarter of 2027.

 

Charlotte Business INClusion

GreenWater Development, Inc. is a city SBE.

 

Established MBE Goal: 7.00%

Committed MBE Goal: 9.56%

GreenWater Development, Inc. exceeded the established contract goal and has committed 9.56% ($105,909) of the total contract amount to the following certified firm(s):

§                     Redstone Materials, Inc. (MBE, SBE) ($55,400) (hauling)

§                     RRC Concrete, Inc. (MBE) ($50,509) (concrete)

 

Established WBE Goal: 4.00%

Committed WBE Goal: 7.56%

GreenWater Development, Inc. exceeded established contract goal and has committed 7.56% ($83,700) of the total contract amount to the following certified firm(s):

§                     On Time Construction, Inc. (WBE, SBE) ($83,700) (masonry)

 

Fiscal Note

Funding: Stormwater Capital Investment Plan

 

Attachments

Attachment(s)

Map