Title
Public Hearing on a Resolution to Close a Portion of Alleyway between Scott Avenue and Fountain View Street
Action
Action:
Continue and conclude the public hearing to close a Portion of Alleyway between Scott Avenue and Fountain View Street
Body
Staff Resource(s):
Debbie Smith, Transportation
Charlie Jones, Transportation
Casey Mashburn, Transportation
Background
* A public hearing to close a Portion of Alleyway between Scott Avenue and Fountain View Street was opened at the March 25, 2024, Council Business Meeting.
* The public hearing was continued until the April 22, 2024, Council Business Meeting to allow for additional time for planning and review of options by surrounding property owners.
* Council has heard from many concerned parties as to the resulting property access created by the proposed alley closure. The petitioner, concerned property owners, and staff have met on multiple occasions to share concerns and potential solutions.
* To resolve the communities' concerns, the petitioner has agreed to the following:
* Widen and improved the public access easement connection to Fountain View Street and add striping to Fountain View Street to enable delivery/trash vehicles to serve the shopping center at 1417 East Boulevard (Collias Dev Co)
* Provide continuous access to 1417 East Blvd (Collias Dev Co) except for the time necessary to conduct the hardscape improvements (driveway, asphalt, etc.)
* Construct a splitter island at the easement connection with Scott Avenue to discourage cut through traffic from the 1315 East Boulevard property.
* Dedicate a new 10' alleyway that is realigned to provide better access to the future public access easement between Scott Avenue and Fountain View Street
Explanation
* NC General Statute Section 160A-299 outlines the procedures for permanently closing streets and alleys.
* The Charlotte Department of Transportation (CDOT) received a petition to abandon public right-of-way and requests this City Council...
Click here for full text