Title: Construct Charlotte Fire Department Firehouse #30
Attachments: 1. Map_Construct Charlotte Fire Department Firehouse #30.pdf

Title

Construct Charlotte Fire Department Firehouse #30

 

Action

Action                     

Approve a contract in the amount of $10,313,000 to the lowest responsive, responsible bidder Swinerton Builders for the Charlotte Fire Department Firehouse #30 project.

 

Body

Staff Resource(s):

Phil Reiger, General Services

Jennifer Smith, General Services

Kathleen Cishek, General Services

 

Explanation

§                     Firehouse #30 was one of three firehouses identified in the Construct Fire Facilities Program within the Fiscal Year 2022 budget.

§                     This project consists of the construction of a new two-story, three-bay firehouse located at 3019 Beam Road in Council District 3.

§                     This new facility will replace the existing firehouse located at 4707 Belle-Oaks Drive, which was built in 1955, and will help improve response times.

§                     This facility will be the first new all-electric firehouse supporting the Strategic Energy Action Plan goal of zero carbon city buildings.

§                     On December 6, 2023, the city issued an Invitation to Bid; ten bids were received.

§                     Swinerton Builders was selected as the lowest responsive, responsible bidder.

§                     The project is anticipated to be complete by first quarter 2026.

 

Charlotte Business INClusion

Established MBE Goal: 8.00%

Committed MBE Goal: 8.30%

Swinerton Builders exceeded the established subcontracting goal and has committed 8.30% ($855,685) of the base bid amount to the following certified firms:

§                     LA Concrete, Inc. (MBE) ($772,095) (building and site concrete)

§                     Taylor Interiors, LLC (MBE, SBE) ($83,590) (air barrier)

 

Established WBE Goal: 2.00%

Committed WBE Goal: 2.56%

Swinerton Builders exceeded the established subcontracting goal and has committed 2.56% ($263,797) of the base bid amount to the following certified firm:

§                     Coleman Contractors, Inc. (WBE) ($263,797) (ceilings, drywall, framing)

 

Fiscal Note

Funding:  General Capital Investment Plan

 