Title: Duke Energy Services for Franklin Water Treatment Plant Substation Construction
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideoAudio
No records to display.
Title
Duke Energy Services for Franklin Water Treatment Plant Substation Construction

Action
Action:
A. Approve a contract for up to $11,500,000 with Duke Energy for the construction of a new substation at the Franklin Water Treatment Plant, and

B. Authorize the City Manager to amend the contract consistent with the purpose for which the contract was approved.

Body
Staff Resource(s):
Angela Charles, Charlotte Water
David Czerr, Charlotte Water
Chuck Bliss, Charlotte Water

Explanation
* Charlotte Water is requesting Duke Energy install a new electrical substation to serve the Franklin Water Treatment Plant in Council District 2.
* The new substation is required as the existing electrical system lacks the capacity to support planned facility upgrades.
* Duke Energy is required to design, install, and approve the substation to meet its standards.
* The project will improve power reliability, support uninterrupted water operations, and allow Charlotte Water to integrate new technologies and expand the facility in the future.
* Duke Energy is completing their construction and demolition work in a phased plan, including design services, construction of the new substation, and demolition of the old substation. This request is for all phases of the work, including construction contingency.
* Construction is anticipated to be complete by the fourth quarter of 2031.

Charlotte Business INClusion
Effective July 1, 2026, Session Law 2026-41 eliminated the authority of North Carolina local governments to use race-conscious and gender-conscious contracting requirements. In compliance with the new law, no MBE/WBE/MWBE/MSBE/WSBE/MWSBE goals or compliance requirements will be included in city contracts. SBE goals are not affected and shall continue to be used in compliance with the CBI program and applicable law.

Small Business Participation
Contract goals were not established for this contract because the scope of work or goods does not present viable subcontracting...