Title: Collective Storm Drainage Improvement Project Series AE
Attachments: 1. Map - Collective SDIP Series AE
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideoAudio
No records to display.

Title

Collective Storm Drainage Improvement Project Series AE

 

Action

Action                     

A.                     Approve a contract in the amount of $1,850,777.50 to the lowest responsive bidder Hux Contracting, LLC (SBE) for the Collective Storm Drainage Improvement Project Series AE, and

 

B.                     Authorize the City Manager to amend the contract consistent with the purpose for which the contract was approved.

 

Body

Staff Resource(s):

Angela Charles, Charlotte Water

Mike Davis, Storm Water Services

Logan Oliver, Storm Water Services

 

Explanation

§                     The contract is part of an ongoing program to provide repairs and/or improvements to storm

drainage systems across the city.

§                     The contract will address storm drainage systems at:

-                     4440 Holbrook Drive in Council District 5, and

-                     4611 Denver Avenue in Council District 3.

§                     On November 4, 2025, the city issued an Invitation to Bid; four bids were received.

§                     Hux Contracting, LLC was selected as the lowest responsive, responsible bidder.

§                     The project is anticipated to be complete by the second quarter of 2027.

 

Charlotte Business INClusion

Established MBE Goal: 8.00%

Committed MBE Goal: 8.02%

Hux Contracting, LLC exceeded the established contract goal and has committed 8.02% ($148,500) of the total contract amount to the following certified firm(s):

§                     Above Average Trucking Co., LLC (MBE, SBE) ($48,500) (hauling)

§                     Shoreline Trucking, LLC (MBE, SBE) ($100,000) (hauling)

 

Established WSBE Goal: 6.00%

Committed WSBE Goal: 6.02%

Hux Contracting, LLC exceeded the established contract goal and has committed 6.02% ($111,500) of the total contract amount to the following certified firm(s):

§                     B & N Grading, Inc. (WBE) ($42,500) (milling and paving)

§                     Carolina Cajun Concrete, Inc. (SBE) ($69,000) (concrete and storm drainage)

 

Fiscal Note

Funding: Stormwater Capital Investment Plan

 

Attachments

Attachment(s)

Map