Title
Municipal Agreement for Relocation and Installation of Water Infrastructure along Asbury Chapel Road
Action
Action:
A. Adopt a resolution authorizing the City Manager to negotiate and execute a municipal agreement with the North Carolina Department of Transportation for construction of water and sanitary sewer line relocations, adjustments, and improvements, and
B. Authorize the City Manager to approve the reimbursement request for the actual cost of the utility construction.
Body
Staff Resource(s):
Angela Charles, Charlotte Water
David Czerr, Charlotte Water
Chuck Bliss, Charlotte Water
Explanation
§ This municipal agreement is for the relocation of water and sanitary sewer infrastructure located within the North Carolina Department of Transportation’s (NCDOT) highway improvements project (BP10-R012 Asbury Chapel Bridge) located along Asbury Chapel Road at South Prong of Clarks Creek (adjacent to Council District 4).
§ As required by NCDOT’s encroachment agreements, the city is financially responsible for the cost to relocate city-owned water and sanitary sewer lines within the state-maintained right-of-way.
§ The city will reimburse NCDOT for actual construction costs at the conclusion of the project.
§ The total estimated city cost of this construction is $1,642,526.
Fiscal Note
Funding: Charlotte Water Capital Investment Plan
Attachments
Attachment(s)
Map
Resolution