Title: Irwin Creek Treatment Plant Phase 2 Project - Construction Change Order 2
Attachments: 1. Irwin Creek WWTP Map

Title

Irwin Creek Treatment Plant Phase 2 Project - Construction Change Order 2

 

Action

Action:                       

Approve change order #2 for $246,336 to Ulliman Schutte Construction, LLC for the Irwin Creek Treatment Plant Phase 2 Project.

 

Body

Staff Resource(s):

Angela Lee, Charlotte Water

Carl Wilson, Charlotte Water

 

Explanation

§                     The Irwin Creek Wastewater Treatment Plant Project is located on Westmont Drive in West Charlotte (City Council District 3). It is one of the oldest treatment plants in Charlotte.

§                     Extensive renovations are ongoing with Ulliman Schutte Construction, LLC.

§                     There are three clarifier tanks that are part of the initial stage of the treatment process.  These tanks are 65 years old and are being rehabilitated as part of the project. During construction, drain valves were found to be leaking and buried air lines were discovered. This project is within budget, and this change order represents additional scope to replace these valves and plug these lines for all three tanks to eliminate the potential for leakage.

§                     Change Order #2 price is $246,336. The new total value of the contract is $43,069,388.

 

Background

§                     The plant is currently undergoing extensive renovations known as the Irwin Creek Phase 2 Project. Construction will be completed in early 2020. 

§                     On January 11, 2016, City Council awarded the low bid price of $39,732,000 to Ulliman Schutte Construction, LLC.

§                     On May 22, 2017, City Council approved Change Order #1 in the amount of $3,091,052 for additional secondary clarifier work.

 

Charlotte Business INClusion

All additional work involved in this Change Order will be performed by Ulliman Schutte Construction, LLC and their existing subcontractors (Part D: Section 6 of the Charlotte Business INClusion Policy). 

 

Fiscal Note

Funding:  Charlotte Water Community Investment Plan

 