Title: Construct Storm Water Repair and Improvements

Title

Construct Storm Water Repair and Improvements

 

Action

Action                     

A.                     Approve a contract in the amount of $5,867,813 to the lowest responsive bidder Onsite Development, LLC, for the Storm Water Repair and Improvement FY2024-G project, and

 

B.                     Authorize the City Manager to amend the contract consistent with the purpose for which the contracts were approved.

 

Body

Staff Resource(s):

Angela Charles, Charlotte Water

Mike Davis, Storm Water Services

Logan Oliver, Storm Water Services

 

Explanation

§                     This contract is part of an ongoing program to provide repairs and/or improvements to storm drainage systems across the city.

§                     Approximately 25 projects may be constructed from this contract, within a contract term not to exceed 24 months. The number of projects may vary depending on the nature and extent of the repairs constructed.

§                     On May 1, 2024, the city issued an Invitation to Bid; three bids were received.

§                     Onsite Development, LLC was selected as the lowest responsive, responsible bidder.

§                     The project is anticipated to be complete by the fourth quarter of 2026.

 

Charlotte Business INClusion

Established MBE Goal: 7.00%

Committed MBE Goal: 7.00%

 

Onsite Development, LLC met the established subcontracting goal and has committed 7.00% ($410,748) of the contract amount to the following certified firm(s):

§                     LJR (MBE, SBE) ($150,000) (concrete)

§                     Streeter (MBE, SBE) ($130,374) (hauling)

§                     Tony’s Trucking (MBE, SBE) ($130,374) (hauling)

 

Established WBE Goal: 4.00%

Committed WBE Goal: 4.00%

 

Onsite Development, LLC met the established subcontracting goal and has committed 4.00% ($234,713) of the contract amount to the following certified firm(s):

§                     Birddog Traffic Control (SBE, WBE) ($234,713) (traffic control)

 

Fiscal Note

Funding: Storm Water Capital Investment Plan