Airport Concourse E Renovation Construction Change Order
Action
Action:
Approve change order #4 for $2,343,806 to the contract with Edison Foard, LLC for the Concourse E Renovation project.
Body
Staff Resource(s):
Haley Gentry, Aviation
Jack Christine, Aviation
Explanation
§ Aviation is in the construction phase for the Concourse E Renovation project.
§ On September 25, 2023, City Council approved a contract in the amount of $44,221,875 with Edison Foard, LLC for the project.
§ The project is primarily funded by a $32.2 million Federal Bipartisan Infrastructure Law Grant under the competitive Airport Terminals Program.
§ The project consists of restroom renovations, new standard Airport signage and wayfinding, new floor and wall finishes, and upgrades to the mechanical, plumbing, and electrical systems to support the renovation.
§ At the time of the original contract, change orders were anticipated as the project scope was further developed.
§ Change Order #1 in the amount of $388,016 was for the removal of three pairs of moving walkways.
§ Change Order #2 in the amount of $18,306 was for a change in the required terrazzo floor aggregate.
§ Change Order #3 was to extend the contract by 27 days due to a delay in receiving the construction permit.
§ This change order will provide for additional steel, ceiling and light fixture changes, temporary moving walkway infill changes, and a general allowance to handle future potential changes during construction.
§ The new total value of the contract is $46,972,003.
Disadvantaged Business Enterprise
All additional work involved with this change order will be performed by Edison Foard, LLC and their existing subcontractor(s):
§ Besco Electrical (DBE) (electric work)
Fiscal Note