Title: Airport Concourse E Renovation Construction Change Order
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideoAudio
No records to display.

Title

Airport Concourse E Renovation Construction Change Order

 

Action

Action                     

Approve change order #4 for $2,343,806 to the contract with Edison Foard, LLC for the Concourse E Renovation project.

 

Body

Staff Resource(s):

Haley Gentry, Aviation

Jack Christine, Aviation

 

Explanation

§                     Aviation is in the construction phase for the Concourse E Renovation project.

§                     On September 25, 2023, City Council approved a contract in the amount of $44,221,875 with Edison Foard, LLC for the project.

§                     The project is primarily funded by a $32.2 million Federal Bipartisan Infrastructure Law Grant under the competitive Airport Terminals Program.

§                     The project consists of restroom renovations, new standard Airport signage and wayfinding, new floor and wall finishes, and upgrades to the mechanical, plumbing, and electrical systems to support the renovation.

§                     At the time of the original contract, change orders were anticipated as the project scope was further developed.

§                     Change Order #1 in the amount of $388,016 was for the removal of three pairs of moving walkways.

§                     Change Order #2 in the amount of $18,306 was for a change in the required terrazzo floor aggregate.

§                     Change Order #3 was to extend the contract by 27 days due to a delay in receiving the construction permit.

§                     This change order will provide for additional steel, ceiling and light fixture changes, temporary moving walkway infill changes, and a general allowance to handle future potential changes during construction.

§                     The new total value of the contract is $46,972,003.

 

Disadvantaged Business Enterprise

All additional work involved with this change order will be performed by Edison Foard, LLC and their existing subcontractor(s):

§                     Besco Electrical (DBE) (electric work)

 

Fiscal Note

Funding:  Aviation Capital Investment Plan