Title: Storm Water Repair and Improvement Projects

Title

Storm Water Repair and Improvement Projects

 

Action

Action:

A.                     Approve a contract in the amount of $759,301.96 to the lowest responsive bidder Hux Contracting LLC (SBE) for the Storm Water Repair and Improvement FY2026-F Projects, and

 

B.                     Authorize the City Manager to amend the contract consistent with the purpose for which the contract was approved.

 

Body

Staff Resource(s):

Angela Charles, Charlotte Water

Mike Davis, Storm Water Services

Logan Oliver, Storm Water Services

 

Explanation

§                     This contract is part of an ongoing program to provide repairs and/or improvements to storm drainage systems across the city.

§                     Approximately 10 projects may be constructed from this contract. The number of projects may vary depending on the nature and extent of the repairs constructed.

§                     On January 20, 2026, the city issued an Invitation to Bid; five bids were received.

§                     Hux Contracting LLC was selected as the lowest responsive, responsible bidder.

§                     The project is anticipated to be complete by the third quarter of 2027.

 

Charlotte Business INClusion 

Hux Contracting LLC is a city-certified SBE.

 

Established MBE Goal: 8.00%

Committed MBE Goal: 8.03%

Hux Contracting LLC exceeded the established contract goal and has committed 8.03% ($61,000) of the total contract amount to the following certified firm(s):

§                     Above Average Trucking Co., Inc. (MBE, SBE) ($36,000) (hauling)

§                     RRC Concrete, Inc. (MBE) ($25,000) (concrete)

 

Established WSBE Goal: 4.00%

Committed WSBE Goal: 4.08%

Hux Contracting LLC exceeded the established contract goal and has committed 4.08% ($31,000) of the total contract amount to the following certified firm(s):

§                     Carolina Cajun Concrete, Inc. (SBE) ($31,000) (concrete and masonry)

 

Fiscal Note

Funding: Stormwater Capital Investment Plan