File #: 15-24424    Version: 1 Name:
Type: Consent Item Status: Approved
File created: 5/8/2025 In control: City Council Business Meeting
On agenda: 6/9/2025 Final action: 6/9/2025
Title: Ideal Way Storm Drainage Improvement Project
Attachments: 1. Map - Ideal Way SDIP

Title

Ideal Way Storm Drainage Improvement Project

 

Action

Action                     

A.                     Approve a contract in the amount of $1,549,196 to the lowest responsive bidder GreenWater Development, Inc. (SBE) for the 816 Ideal Way Storm Drainage Improvement Project, and

 

B.                     Authorize the City Manager to amend the contract consistent with the purpose for which the contract was approved.

 

Body

Staff Resource(s):

Angela Charles, Charlotte Water

Mike Davis, Storm Water Services

Logan Oliver, Storm Water Services

 

Explanation

§                     This project will reduce flooding and replace aging infrastructure along Ideal Way from McDonald Avenue to Park Road and along Kirkwood Avenue from Magnolia Avenue to Ideal Way in Council District 1.

§                     The work includes grading, storm drainage, water, sanitary sewer, curb and gutter, and asphalt paving.

§                     On April 4, 2025, the city issued an Invitation to Bid; four bids were received.

§                     GreenWater Development, Inc. was selected as the lowest responsive, responsible bidder.

§                     The project is anticipated to be complete by the second quarter of 2026.

 

Charlotte Business INClusion 

GreenWater Development, Inc. is a city certified SBE.

 

Established MBE Goal: 8.00%

Committed MBE Goal: 8.03%

GreenWater Development, Inc. exceeded the established contract goal and has committed 8.03% ($124,344) of the total contract amount to the following certified firm(s):

§                     Redstone Materials, Inc. (MBE, SBE) ($90,384) (hauling)

§                     RRC Concrete, Inc. (MBE) ($33,960) (concrete)

 

Established WBE Goal: 4.00%

Committed WBE Goal: 10.19%

GreenWater Development, Inc. exceeded the established contract goal and has committed 10.19% ($157,800) of the total contract amount to the following certified firm(s):

§                     On Time Construction, Inc. (WBE, SBE) ($157,800) (masonry)

 

Fiscal Note

Funding:  Stormwater Capital Investment Plan

 