Title
Water Transmission Main Improvements and Repairs
Action
Action:
Approve a guaranteed maximum price of $1,771,448.00 to State Utility Contractors, Inc. for Design-Build Construction services for the Water Transmission Main Improvements and Repairs project.
Body
Staff Resource(s):
Angela Charles, Charlotte Water
David Czerr, Charlotte Water
Carl Wilson, Charlotte Water
Explanation
§ State Utility Contractors, Inc. developed a guaranteed maximum price (GMP) to construct approximately 2,600 linear feet of 12-inch water line along Oakdale and Peachtree Roads, with a connection of 600 linear feet of eight-inch water line along Ferrell Road (Council District 2).
§ On June 8, 2020, City Council approved a contract with State Utility Construction, Inc. for Design-Build design services. Based on the design, a GMP for construction services was developed.
• The project is anticipated to be complete by third quarter 2024.
Charlotte Business INClusion
The city negotiates participation for Design-Build contracts after scopes of work defined for construction services. State Utility Contractors, Inc. has committed ($245,904) or 13.88% of the total contract for construction services to the following certified firms:
§ Fuller & Co. Construction, LLC (SBE) ($122,200) (temporary water services)
§ Trull Contracting, LLC (SBE, WBE) ($83,204) (asphalt and concrete)
§ Sanders Constructors, Inc. (SBE) ($37,000) (clearing)
§ Lawrence Associates, PA (SBE) ($3,500) (surveying)
Fiscal Note
Funding: Charlotte Water Capital Investment Plan
Attachments
Attachment(s)
Map