File #: 15-23066    Version: 1 Name:
Type: Consent Item Status: Approved
File created: 7/24/2024 In control: City Council Business Meeting
On agenda: 9/9/2024 Final action: 9/9/2024
Title: Engineering Services for Ashe Plantation Phase II Upgrades
Attachments: 1. Map - Engineering Services for Ashe Plantation Phase II Upgrades

Title

Engineering Services for Ashe Plantation Phase II Upgrades

 

Action

Action:

A.                     Approve contract amendment #1 for $489,500 to the contract with Highfill Infrastructure Engineering, P.C. for construction administration and observation services, and

 

B.                     Authorize the City Manager to amend the contract consistent with the purpose for which the contract and this amendment were approved.

 

Body

Staff Resource(s):

Angela Charles, Charlotte Water

Ron Hargrove, Charlotte Water

Joseph Lockler, Charlotte Water

 

Explanation

§                     On May 5, 2024, the city entered into an engineering services contract with Highfill Infrastructure Engineering, P.C. for a capacity study of Ashe Plantation Wastewater Treatment Plant (WWTP), located in the Town of Mint Hill (adjacent to Council District 5).

§                     Amendment #1 will provide construction bidding, administration, and observation services for the construction of a replacement WWTP.

§                     The new value of the contract, including amendment #1 is $589,200.

 

Charlotte Business INClusion

All additional work involved in this Amendment will be performed by the Highfill Infrastructure Engineering, P.C. and their existing subconsultants. Highfill Infrastructure Engineering, P.C. is a city SBE and has committed 12.46% ($61,000) of the total contract Amendment to the following certified firm(s):

§                     Southeastern Consulting Engineers, Inc. (SBE) ($61,000) (electrical engineering services)

 

Fiscal Note

Funding:  Charlotte Water Capital Investment Plan

 