Title: South End Station Pre-Construction Services
Attachments: 1. Map - CMAR Pre-Construction Services
Title
South End Station Pre-Construction Services

Action
Action:
A. Award a Construction Manager at Risk contract in an amount not to exceed $1,322,694 with Stacy Witbeck for pre-construction services to assist with the design of a new light rail station in South End, and

B. Authorize the City Manager to negotiate and execute amendments to the contract consistent with the purpose for which the contract was approved.

Body
Staff Resource(s):
Brent Cagle, CATS
Kelly Goforth, CATS
Todd Thorne, CATS

Explanation
* The South End Station project will construct a new light rail station and Rail Trail improvements on the LYNX Blue Line between the New Bern and East/West Boulevard Stations, located in Council District 3.
* The city has selected the Construction Manager at Risk (CMAR) project delivery method to provide more effective coordination, better control of project costs and schedule, and to better mitigate risks during construction.
* As the CMAR, Stacy Witbeck will be responsible for pre-construction services that include:
* Coordinating with the project team to plan construction activities in order to minimize impacts to the community, local businesses and LYNX Blue Line operations;
* Reviewing project documents and providing expertise in regard to constructability, value engineering, procurement and construction risk;
* Cost estimating and cost control; and
* Construction scheduling.
* On June 14, 2023, the city issued a Request for Proposal (RFP) for a CMAR for the entire project. No proposals were received.
* CATS re-evaluated and separated the work into two separate packages, Track/Systems and Civil/Station.
* On February 23, 2024, the city issued a RFP for a Track/Systems CMAR; two responses were received.
* Stacy Witbeck is the best qualified firm to meet the city's needs based on demonstrated competence, cost, and related project experience in response to the RFP requirements.
* Council will be asked to approve future contracts related to constructi...