File #: 15-25856    Version: 1 Name:
Type: Consent Item Status: Agenda Ready
File created: 3/10/2026 In control: City Council Business Meeting
On agenda: 5/11/2026 Final action:
Title: Remount Road at West Boulevard Intersection Improvements
Attachments: 1. Map - Remount Rd at West Blvd Intersection Improvements
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideoAudio
No records to display.

Title

Remount Road at West Boulevard Intersection Improvements

 

Action

Action                     

Approve a contract in the amount of $1,286,501.70 to the lowest responsive, responsible bidder Husky Construction Corp. for the Remount Road at West Boulevard Intersection Improvements Project.

 

Body

Staff Resource(s):

Phil Reiger, General Services

Kathleen Cishek, General Services

Keith Bryant, General Services

 

Explanation

§                     This project will improve mobility and safety at the intersection of Remount Road and West Boulevard located in Council District 3 and the West Boulevard Corridor of Opportunity. 

§                     Improvements will increase pedestrian walkability, improve transit access, and support placemaking while incorporating the history and culture of the surrounding community along the corridor.

§                     Work will include sidewalks, a decorative plaza, concrete seat walls, bus shelters with amenities, landscaping, and public art.

§                     On February 24, 2026, the city issued an Invitation to Bid; six bids were received.

§                     Husky Construction Corp. was selected as the lowest responsive, responsible bidder.

§                     The project is anticipated to be complete by the first quarter of 2028.

 

Charlotte Business INClusion

Established MBE Goal: 5.00%

Committed MBE Goal: 5.83%

Husky Construction Corp. exceeded the established subcontracting goal and has committed 5.83% ($75,000) of the total contract amount to the following certified firm(s):

§                     Streeter Trucking Company Inc. (MBE) ($75,000) (hauling)

 

Established WSBE Goal: 14.00%

Committed WSBE Goal: 14.69%

Husky Construction Corp. exceeded the established subcontracting goal and has committed 14.69% ($189,000) of the total contract amount to the following certified firm(s):

§                     C & M Recycling, Inc. (WBE) ($8,000) (materials)

§                     JM Custom Construction LLC (WSBE) ($181,000) (concrete)

 

Fiscal Note

Funding: General Capital Investment Plan

 