Title
Lyndhurst Avenue Storm Drainage Repair
Action
Action:
Award a contract in the amount of $405,196.67 to the lowest responsive bidder D.E. Walker Construction Co. for the Lyndhurst Avenue Storm Drainage Repair project.
Body
Staff Resource(s):
Jennifer Smith, Engineering & Property Management
Explanation
* The project involves installing approximately 330 feet of new storm drainage and replacing associated utilities along Lyndhurst Avenue between East Boulevard and East Kingston Avenue.
* The work will include:
* Storm drainage,
* Sidewalk,
* Curb and gutter,
* Driveways,
* Accessible ramps,
* Asphalt pavement replacement,
* Water line approximately 460 feet, and
* Sanitary sewer approximately 600 feet.
* On August 12, 2015, the City issued an Invitation to Bid for 1712 Lyndhurst Avenue Storm Water Repair Project; seven bids were received from interested service providers.
* D.E. Walker Construction Co. was selected as the lowest responsive, responsible bidder.
* The project is anticipated to be complete by second quarter 2016.
Charlotte Business INClusion
Established SBE Goal: 13%
Committed SBE Goal: 18.11%
D.E. Walker Construction Co., a City SBE, exceeded the established SBE subcontracting goal, and has committed 18.11% ($73,397.50) of the total contract amount to the following certified firms (Part B: Section 3 of the Charlotte Business INClusion Policy):
* Express Logistics Services, Inc. (SBE, MBE) ($40,750) (hauling)
* Kingdom Trucking (SBE) ($20,400) (hauling)
* RJJ Construction LLC (SBE) ($12,247.50) (concrete curb)
Established MBE Goal: 5%
Committed MBE Goal: 10.06%
D.E. Walker Construction Co. exceeded the established MBE subcontracting goal, and has committed 10.06% ($40,750) of the total contract amount to the following certified firm (Part B: Section 3 of the Charlotte Business INClusion Policy):
* Express Logistics Services, Inc. (SBE, MBE) ($40,750) (hauling)
Fiscal Note
Funding: Storm W...
Click here for full text