Title: Airport South Crossfield Taxiway Construction Change Order
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideoAudio
No records to display.
Title
Airport South Crossfield Taxiway Construction Change Order

Action
Action:
Approve change order #7 for $567,609.80 to the contract with Hi-Way Paving, Inc. for the Deicing Pad and South Crossfield Taxiway Project Package 2.

Body
Staff Resource(s):
Haley Gentry, Aviation
Jack Christine, Aviation

Explanation
* The Deicing Pad and South Crossfield Taxiway Project consists of three packages of work, which will increase airfield operational efficiency. Construction activities in these three packages include the extension of Taxiway F, construction of a new cross-field taxiway connecting the center and eastern-most runways, and relocation of existing aircraft deicing pads from the cargo area to the south end of the center runway.
* On February 13, 2023, City Council approved a contract in the amount of $75,551,803.60 with Hi-Way Paving, Inc. for the Deicing Pad and South Crossfield Taxiway Project Package 2 for pavement and lighting for the new taxiway extensions and deicing pad.
* On May 22, 2023, City Council approved Change Order #1 in the amount of $4,162,113 to Hi-Way Paving, Inc. to provide for earthwork that was descoped from Package 1 and added to Package 2.
* Change Order #2 was to extend the contract by one day due to weather impacts.
* Change Order #3 was to extend the contract by two days due to weather impacts.
* Change Order #4 in the amount of $456,895.22 was for regional detention basin maintenance for managing stormwater flow and replacing cement-treated bases during concrete demolition.
* Change Order #5 in the amount of $18,517.57 was for replacing electrical manhole covers.
* Change Order #6 was to extend the contract by two days due to weather impacts.
* This change order will provide for additional earthwork and reorienting electrical junction boxes for conduit installation.
* The new total value of the contract is $80,756,939.19.

Disadvantaged Business Enterprise
All additional work involved with this change order will be pe...