Action:
A. Adopt a resolution authorizing the City Manager to execute a municipal agreement with the Town of Huntersville for construction of water infrastructure improvements, and
B. Authorize the City Manager to approve the reimbursement request for the actual cost of the utility construction.
Body
Staff Resource(s):
Angela Charles, Charlotte Water
David Czerr, Charlotte Water
Carl Wilson, Charlotte Water
Explanation
§ This project will replace water line along Gibson Park Drive in the Town of Huntersville (adjacent to Council District 4).
§ This is a Town of Huntersville project that is being administered and funded by the town.
§ The Town of Huntersville requires that the city enter into a municipal agreement for the replacement of city-owned water lines within the town’s roadway projects prior to construction.
§ The city will reimburse the Town of Huntersville for actual construction costs at the conclusion of the project.
§ The total estimated city cost of this construction is $315,400.
Fiscal Note
Funding: Charlotte Water Capital Investment Plan