Title: Airport Concourse A Expansion Phase 2 Change Order

Title

Airport Concourse A Expansion Phase 2 Change Order

 

Action

Action                     

Approve change order #3 for $4,670,042.19 to JE Dunn-McFarland, A Joint Venture, for construction manager at risk services for the Concourse A Expansion Phase 2 project.

 

Body

Staff Resource(s):

Haley Gentry, Aviation

Jack Christine, Aviation

 

Explanation

§                     On March 28, 2022, City Council approved a contract in the amount of $172,599,811.11 with JE Dunn-McFarland, A Joint Venture, for construction manager at risk services for the Concourse A Expansion Phase 2 (CAP2) project.

§                     At the request of the airlines, the project added a new baggage handling system (BHS) Make-up Device (MU8) Expansion at Concourse A. CAP2 was designed in a manner that could be expanded when the airlines required more baggage make-up space. Passenger numbers now require the added capacity this project will provide.

§                     On August 28, 2023, City Council approved contract amendment #1 in the amount of $3,549,014.48 to JE Dunn-McFarland, A Joint Venture, for the foundations and structure of the mid-connector expansion to enclose the MU8 for the CAP2 project.

§                     On January 8, 2024, City Council approved contract amendment #2 in the amount of $4,832,230.44 to JE Dunn-McFarland, A Joint Venture, for the remainder of the building expansion required for housing the MU8 expansion.

§                     This change order will provide for the purchase and installation of the BHS equipment. This is the final change order anticipated for the additional scope requested by the airlines.

§                     The new total value of the contract is $185,651,098.22.  

 

Disadvantaged Business Enterprise

The DBE goal for this project is 10.00%.

 

All additional work involved with this change order will be performed by JE Dunn-McFarland, A Joint Venture and their existing subconsultants and subcontractors.

 

Fiscal Note

Funding:  Aviation Capital Investment Plan