Title: Clarke Creek Pump Station and Forcemain Construction
Attachments: 1. Map-Clarke Creek Pump Station and Forcemain Construction
Title
Clarke Creek Pump Station and Forcemain Construction

Action
Action:
Approve a guaranteed maximum price of $21,138,774.00 to State Utility Contractors, Inc. for Design-Build construction services for the Clarke Creek Pump Station and Forcemain project.

Body
Staff Resource(s):
Angela Charles, Charlotte Water
David Czerr, Charlotte Water
Carl Wilson, Charlotte Water

Explanation
* State Utility Contractors, Inc. has developed a guaranteed maximum price (GMP) for design services, procurement of materials, and construction related to the proposed Clarke Creek Pump Station and associated improvements, located in the Town of Huntersville (adjacent to Council Districts 2 and 4).
* On February 14, 2022, City Council approved a contract for $5,668,010 with State Utility Contractors, Inc. for Design-Build design services. Based on the design, GMPs for construction services are developed.
* City Council will receive future requests for the approval of additional GMPs for construction once established.

Charlotte Business INClusion
The city negotiates subcontracting participation for Design-Build contracts after the firm is selected and scopes of work are defined for design and construction services (Part G: Section 2.4 of the Charlotte Business INClusion Policy). State Utility Contractors, Inc. has committed $2,913,631 or approximately 13.78% of the total contract for construction services to the following certified firms:
* Smart Electric Company, Inc. (WBE) ($1,458,966) (electrical construction)
* Fuller and Co. Construction, LLC (SBE) ($483,000) (bore and jack)
* Buffkin Trucking, Inc. (MBE, SBE) ($186,000) (stone hauling)
* Shoreline Trucking, LLC (MBE, SBE) ($150,000) (hauling)
* Soggy Bottom Erosion Control, LLC (SBE) ($98,200) (erosion control)
* Martin Landscaping Co. Inc. (MBE, SBE) ($88,550) (seeding and matting
* Ram Pavement Services, Inc. (SBE) ($80,000) (asphalt paving)
* Sanders Constructors (SBE) ($76,500) (clearing)
* Gavel & Dorn Engineering, ...