Title
Stowe Regional Water Resource Recovery Facility Equipment
Action
Action:
Approve a guaranteed maximum price of $15,869,000 to Crowder/Garney JV for the purchase of equipment needed for Design-Build construction services for the Stowe Regional Water Resource Recovery Facility project.
Body
Staff Resource(s):
Angela Charles, Charlotte Water
David Czerr, Charlotte Water
Ron Hargrove, Charlotte Water
Explanation
§ Crowder/Garney JV has developed a guaranteed maximum price (GMP) for the purchase of equipment required for construction of the Stowe Regional Water Resource Recovery Facility (SRWRRF) project (adjacent to Council Districts 2 and 3).
§ The SRWRRF will treat flows from the existing Long Creek basin and flows from the cities of Mount Holly and Belmont.
§ On April 27, 2020, City Council approved a contract for $6,911,323 with Crowder/Garney JV for the first phase of Design-Build design services. Crowder/Garney JV evaluated and assisted Charlotte Water in selecting specific design options.
§ On January 25, 2021, City Council approved an amendment for $24,504,784 for the final phase of Design-Build design services. Crowder/Garney JV provided detailed design services.
§ City Council will receive future requests for the approval of remaining construction related GMPs once established. The SRWRRF is estimated to be in operation by second quarter 2026.
Charlotte Business INClusion
The City negotiates participation for Design-Build contracts after the firm is selected and scopes of work are defined for design and construction services (Part G: Section 2.4 of the Charlotte Business INClusion Policy). This contract is solely for the purchase of equipment and therefore does not have subcontracting opportunities.
Fiscal Note
Funding: Charlotte Water Capital Investment Plan
Attachments
Attachment(s)
Map