Title: Stowe Regional Water Resource Recovery Facility Access Drive
Attachments: 1. Map-Stowe Regional Water Resource Recovery Facility Access Drive

Title

Stowe Regional Water Resource Recovery Facility Access Drive

 

Action

Action                     

Approve a contract in the amount of $7,984,332.62 to the lowest responsive bidder Blythe Development Company for the Stowe Regional Water Resource Recovery Facility Access Drive project.

 

Body

Staff Resource(s):

Angela Charles, Charlotte Water

David Czerr, Charlotte Water

Carl Wilson, Charlotte Water

 

Explanation

§                     This contract is for the construction of the access road to the Stowe Regional Water Resource Recovery Facility that is also under construction (adjacent to Council Districts 2 and 3).

§                     On October 19, 2022, the city issued an Invitation to Bid; three bids were received.

§                     Blythe Development Company was selected as the lowest responsive, responsible bidder.

§                     The project is anticipated to be complete by fourth quarter 2023.

 

Charlotte Business INClusion

Established MBE Goal: 3.00%

Committed MBE Goal: 3.01%

Blythe Development Company met the established MBE subcontracting goal and has committed 3.01% ($240,000) of the total contract amount to the following certified firms (Part B: Section 3 of the Charlotte Business INClusion Policy):

§                     Express Logistics Services, Inc. (MBE, SBE) ($240,000) (hauling)

 

Established SBE Goal: 7.00%

Committed SBE Goal: 7.01%

Blythe Development Company met the established SBE subcontracting goal and has committed 7.01% ($560,000) of the total contract amount to the following certified firms (Part B: Section 3 of the Charlotte Business INClusion Policy):

§                     Erosion Defence (SBE) ($405,200) (erosion control)

§                     Diamond Trucking of NC, Inc. (MBE, SBE) ($113,060) (hauling)

§                     Pentacle, Inc. (SBE, WBE) ($28,900) (fencing)

§                     Striping Concepts, LLC (SBE) ($12,840) (pavement marking)

 

Fiscal Note

Funding: Charlotte Water Capital Investment Plan

 