Title
Fourth Parallel Runway - Early Grading Change Order
Action
Action:
Approve change order #1 for $3,657,630.53 to ES Wagner Company, LLC for the Fourth Parallel Runway - Early Grading project.
Body
Staff Resource(s):
Haley Gentry, Aviation
Jack Christine, Aviation
Explanation
§ Aviation is in the design phase for the Fourth Parallel Runway Program which will enhance airfield capacity and operational efficiency.
§ On March 13, 2023, City Council approved a contract in the amount of $44,589,894.76 with ES Wagner Company, LLC for the Fourth Parallel Runway - Early Grading project.
§ The project consists of grading, drainage, fencing, erosion and sediment control, tree clearing, sanitary sewer installation, concrete box culvert extension and duct bank installation.
§ This change order will provide modifications to proposed communication duct bank and storm drain systems, and the removal of compost stockpiles left by the closed composting facility.
§ Including these work elements in the current contract allows for a more compact project schedule as the final design packages are completed over the next six months.
§ The new total value of the contract is $48,247,525.29.
Disadvantaged Business Enterprise
Established DBE Goal: 14.00%
Committed DBE Goal: 14.15%
All work involved in this change order will be performed by ES Wagner Company, LLC and their existing subcontractors.
Fiscal Note
Funding: Aviation Capital Investment Plan