Title: Contract Amendment for Gum Branch Outfall Inspection Services
Attachments: 1. Gum Branch Map

Title

Contract Amendment for Gum Branch Outfall Inspection Services

 

Action

Action:

Approve contract amendment #1 for $204,146 to the Gum Branch Outfall Contract with Stantec Consulting Services Inc. for construction management services.

 

Body

Staff Resource(s):

Angela Lee, Charlotte Water

Carl Wilson, Charlotte Water

 

Explanation

§                     The Gum Branch outfall is located in the Long Creek sewer basin (City Council District 2), and conveys wastewater flows from northwest Charlotte and northwestern Mecklenburg County to the McAlpine Creek Wastewater Treatment Plant.

§                     In order to address both the condition and capacity constraints of the outfall, the Gum Branch project includes the construction of approximately 5,600 linear feet of 30 inch gravity sewer and 4,400 linear feet of 24 inch gravity sewer.

§                     On June 13, 2016, City Council approved the original contract for engineering, construction administration and part-time construction inspection services in the amount of $491,819.

§                     This amendment will cover full-time construction inspection services by Stantec Consulting Services Inc., as well as the additional duration needed to complete construction based on increased complexity of the project.

§                     The new contract amount including the contract amendment is $695,965.

 

Charlotte Business INClusion

No subcontracting goal was established because there are no opportunities (Part C: Section 2.1(a) of the Charlotte Business INClusion Policy).

 

Fiscal Note

Funding:  Charlotte Water Community Investment Plan

 