Title
6317 Birmingham Drive Storm Drainage Improvement Project
Action
Action:
A. Approve a contract in the amount of $2,223,871.20 to the lowest responsive, responsible bidder DOT Construction Inc. for the 6317 Birmingham Drive Storm Drainage Improvement Project, and
B. Authorize the City Manager to amend the contract consistent with the purpose for which the contract was approved.
Body
Staff Resource(s):
Angela Charles, Charlotte Water
Mike Davis, Storm Water Services
Logan Oliver, Storm Water Services
Explanation
§ This project will replace aging infrastructure along Birmingham Drive, Burnt Mill Road, and Tempsford Lane in Council District 6.
§ The work includes grading, storm drainage, water, sanitary sewer, curb and gutter, sidewalk, and asphalt paving.
§ On April 7, 2026, the city issued an Invitation to Bid; four bids were received.
§ DOT Construction Inc. was selected as the lowest responsive, responsible bidder.
§ The project is anticipated to be complete by the fourth quarter of 2027.
Charlotte Business INClusion
Established MBE Goal: 8.00%
Committed MBE Goal: 8.00%
DOT Construction Inc. met the established contract goal and has committed 8.00% ($177,910) of the total contract amount to the following certified firm(s):
§ Streeter Trucking Company Inc. (MBE, SBE) ($177,910) (hauling)
Established WSBE Goal: 5.00%
Committed WSBE Goal: 5.00%
DOT Construction Inc. met the established contract goal and has committed 5.00% ($111,194) of the total contract amount to the following certified firm(s):
§ Clear Creek of Salisbury Inc. (WBE, SBE) ($111,194) (concrete and asphalt)
Fiscal Note
Funding: Storm Water Capital Investment Plan
Attachments
Attachment(s)
Map