Title
North Summit Avenue Storm Drainage Improvement Project
Action
Action:
Award a contract in the amount of $260,778.10 to the lowest responsive bidder Husky Construction Corp. for the 325 North Summit Avenue Storm Drainage Improvement project.
Body
Staff Resource(s):
Stewart Edwards, Engineering & Property Management
Explanation
§ The project involves installation of approximately 700 feet of new storm drainage to reduce flooding of streets and homes from Frazier Avenue to the outfall at North Summit Avenue.
§ The work will include:
- Storm drainage,
- Milling and overlay of the existing road,
- Driveways,
- Sidewalk, and
- Curb and gutter.
§ On September 17, 2015, the City issued an Invitation to Bid for 325 North Summit Avenue; five bids were received from interested service providers.
§ Husky Construction Corp. was selected as the lowest responsive, responsible bidder.
§ The project is anticipated to be complete by the second quarter of 2016.
Charlotte Business INClusion
Construction contracts estimated to be less than $300,000 are informal and are exempt from the goal setting process (Part A: Section 3.1 of the Charlotte Business INClusion Policy). Husky Construction is a City SBE.
Fiscal Note
Funding: Storm Water Community Investment Plan