Airport Fourth Parallel Runway 1C-19C and Connectors Change Order

Action
Action:
A. Approve change order #3 for $9,638,706.46 to the contract with Hi-Way Paving, Inc. and ES Wagner Company, LLC, a Joint Venture, for the Fourth Parallel Runway 1C-19C and Connectors Project,

B. Authorize the City Manager to execute a Specific Operating Agreement with the University of North Carolina at Charlotte for the Airfield Pavement Management System - Digital Twin Technology research initiative, and

C. Authorize the City Manager to amend the Specific Operating Agreement consistent with the purpose for which the agreement was approved.

Body
Staff Resource(s):
Haley Gentry, Aviation
Jack Christine, Aviation

Background
* The Fourth Parallel Program will enhance airfield capacity and operational efficiency and reduce the number of active runway crossings.
* This project includes the construction of Runway 1C-19C and associated connector taxiways.
* The project is anticipated to be complete by the first quarter of fiscal year 2028.

Explanation
Action A
* On December 9, 2024, City Council approved a contract with Hi-Way Paving, Inc. and ES Wagner Company, LLC, a Joint Venture, for $163,084,231 for the Fourth Parallel Runway 1C-19C and Connectors project.
* Change order #1 was to extend the contract by one day due to weather delays and did not impact the total value of the contract.
* Change order #2 was to extend the contract by five days due to weather and operational delays and did not impact the total value of the contract.
* Change order #3 will provide for runway nomenclature marking and signage updates to the three existing parallel runways in preparation for the fourth parallel runway becoming operational and the installation of an Airfield Pavement Management System in partnership with University of North Carolina at Charlotte's Aviation Innovation and Research (AIR) Institute.
* This change order is necessary due to receiving no bids on three differen...