Title
Municipal Agreement for Relocation of Water and Sanitary Sewer Infrastructure
Action
Action:
A. Adopt a resolution authorizing the City Manager to negotiate and execute a municipal agreement with the North Carolina Department of Transportation for construction of water and sanitary sewer line relocations, adjustments, and improvements, and
B. Authorize the City Manager to approve the reimbursement request for the actual cost of the utility construction.
Body
Staff Resource(s):
Angela Charles, Charlotte Water
David Czerr, Charlotte Water
Carl Wilson, Charlotte Water
Explanation
§ This municipal agreement is for the relocation and replacement of water and sanitary sewer infrastructure located within the North Carolina Department of Transportation’s (NCDOT) highway improvements project (Project U-5873), located along Main Street (NC Highway 115), Davidson Street, and Potts Street in the Town of Cornelius (adjacent to Council District 4).
§ As required by the NCDOT’s encroachment agreements, the city is financially responsible for the cost to relocate city-owned water and sanitary sewer lines within the state-maintained right-of-way.
§ The city will reimburse the NCDOT for actual construction costs at the conclusion of the project.
§ The total estimated city cost of this construction is $2,200,000.
Fiscal Note
Funding: Charlotte Water Capital Investment Plan
Attachments
Attachment(s)
Map
Resolution