Title
Rose Valley Drive Storm Water Improvement Project
Action
Action:
Award a contract in the amount of $1,411,105.30 to the lowest responsive bidder Hall Contracting Corporation for the Rose Valley Drive Storm Water Improvement Project.
Body
Staff Resource(s):
Mike Davis, Engineering and Property Management
Stewart Edwards, Engineering and Property Management
Explanation
* This project will address failing storm drainage systems on Rose Valley Drive, Stonewood Drive and Brookhaven Road. It is located in Council District 6.
* Work will include the installation of 1,665 linear feet of concrete pipe, 100 linear feet of pipe lining, associated drainage structures, curb, gutter and asphalt paving.
* On January 22, 2018, the City issued an Invitation to Bid; six bids were received from interested service providers.
* Hall Contracting Corporation was selected as the lowest responsive, responsible bidder.
* The project is anticipated to be completed in second quarter 2019.
Charlotte Business INClusion
Established SBE Goal: 20.00%
Committed SBE Goal: 22.67%
Hall Contracting Corporation exceeded the established subcontracting goal, and has committed 22.67% ($319,897.56) of the total contract amount to the following certified firms (Part B: Section 3 of the Charlotte Business INClusion Policy):
* Trull Contracting (SBE) (asphalt) ($114,794.25)
* On Time Construction (SBE, MBE) (concrete) ($70,798.70)
* Silverback Brothers (SBE, MBE) (hauling) ($66,338.25)
* All Points Trucking (SBE) (hauling) ($41,570.74)
* Bird Dog Traffic Control (SBE) (traffic control) ($12,300.62)
* Whitesell Trucking (SBE) (clearing/grubbing) ($10,900)
* A-1 Precision Fence (SBE) (fencing) ($3,195)
Established MBE Goal: 7.00%
Committed MBE Goal: 9.72%
Hall Contracting Corporation exceeded the established subcontracting goal, and has committed 9.72% ($137,136.95) of the total contract amount to the following certified firms (Part B: Section 3 of the Charlotte Business INClusion Policy):
* ...