Title
Construct Storm Drainage Improvement Projects
Action
Action:
Approve a contract in the amount of $2,786,198.20 to the lowest responsive bidder OnSite Development, LLC for the construction of storm drainage improvement projects.
Body
Staff Resource(s):
Angela Lee, General Services
Kruti Desai, General Services
Susan Tolan, General Services
Explanation
* This contract is part of an ongoing program to provide repairs and/or improvements to storm drainage systems.
* This contract will address failing storm drainage systems in the following locations:
* 1301 Ranch Road (Council District 2),
* 1308 Interurban Avenue (Council District 2),
* 7259 Point Lake Drive (Council District 5),
* 1331 Kingscross Drive (Council District 6),
* 2114 Shadyview Drive (Council District 6),
* 2217 Archdale Drive (Council District 6), and
* 11143 Ballantyne Crossing Avenue (Council District 7).
* Work will also include grading, drainage, sidewalks, and curb and gutter.
* On July 5, 2019, the city issued an Invitation to Bid for "Collective Storm Drainage Improvement Projects Series C"; four bids were received.
* OnSite Development LLC was selected as the lowest responsive, responsible bidder.
* The project is anticipated to be complete by end of fourth quarter 2020.
Charlotte Business INClusion
Established SBE Goal: 19.00%
Committed SBE Goal: 27.13%
OnSite Development, LLC exceeded the established SBE subcontracting goal, and has committed 27.13% ($755,814) of the total contract amount to the following certified firms (Part B: Section 3 of the Charlotte Business INClusion Policy):
* AMP Utility Distribution Services, LLC (SBE) ($125,000) (utility materials)
* R.R.C. Concrete Inc (SBE, MBE) ($75,000) (concrete)
* Affordable Source Trucking, LLC (SBE, MBE) ($107,162.80) (hauling)
* JV Trucking, LLC (SBE) ($107,162.80) (hauling)
* MTS Trucking Inc. (SBE, MBE) ($107,162.80) (hauling)
* Solanos Trucking Company, Inc. (SBE) ($107,162.80) (hauling)
* Tony's Trucking Company, ...