Title
Cherokee Scotland Storm Drainage Improvement Project Change Order #2
Action
Action:
Approve change order #2 for $294,525 to OnSite Development, LLC for the Cherokee Scotland Storm Drainage Improvement Project.
Body
Staff Resource(s):
Gina Shell, Engineering and Property Management
Susan Tolan, Engineering and Property Management
Jackie Bray, Engineering and Property Management
Explanation
§ The Cherokee/Scotland project includes installation of over 10,000 feet of storm drainage infrastructure.
§ Change Order #1 in the amount of $788,921.85 was approved by City Council on February 8, 2016. This change order provided funding for additional sewer replacement on Biltmore Drive and extended the contract completion to September 2017.
§ Change Order #2 in the amount of $294,525 will accommodate backfill material underestimated at the time of bid.
§ The contractor will be paid the original contract unit price for the backfill material.
§ The total contract value including this change order is $7,450,607.58, which is available within the project budget.
§ The project is scheduled to be complete by the third quarter of 2017.
Charlotte Business INClusion
Additional work will be performed by OnSite Development and their existing subcontractors (Part D: Section 6 of the Charlotte Business INClusion Policy).
Fiscal Note
Funding: Storm Water Community Investment Plan