Title: Beatties Ford Sunset Pedestrian Improvements Phase 1
Attachments: 1. Map - Beatties Ford Sunset Pedestrian Improvements Phase 1
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideoAudio
No records to display.

Title

Beatties Ford Sunset Pedestrian Improvements Phase 1

Action

Action                     

Authorize the City Manager to execute a contract in the amount $5,871,879 to the lowest responsive, responsible bidder Zoladz Construction Company, Inc. for the Beatties Ford Sunset Pedestrian Improvements Phase 1 project.

 

Body

Staff Resource(s):

Phil Reiger, General Services

Kathleen Cishek, General Services

Keith Bryant, General Services

 

Explanation

§                     This project will improve pedestrian and bicycle connectivity and safety along Sunset Road from Day Lily Lane to Kiev Drive in Council District 2.

§                     Work will include new sidewalk, wheelchair ramps, curb and gutter, drainage improvements, driveway improvements, and pavement markings.

§                     On September 19, 2024, the city issued an Invitation to Bid; four bids were received.

§                     Zoladz Construction Company, Inc. was selected as the lowest responsive, responsible bidder.

§                     This is a joint project between the city and the North Carolina Department of Transportation (NCDOT). NCDOT received Federal Highway Administration (FHWA) authorization for the construction phase of this project in the amount of $1,870,000. 

§                     Contract will be awarded upon review and approval by NCDOT.

§                     This project is anticipated to be complete by the fourth quarter of 2027.

 

Disadvantage Business Enterprise

Established DBE Goal: 5.00%

Committed DBE Goal: 7.78%

Zoladz Construction Company, Inc. exceeded the established contract goal and has committed 7.78% ($456,567) of the total contract amount to the following certified firm(s):

§                     RRC Concrete, Inc. (DBE) ($456,567) (gutters, curbs, sidewalk, driveways, concrete, wheelchair ramps)

 

Fiscal Note

Funding:  General Capital Investment Plan and FHWA funds

 