Title: Providence Road Sidewalk Project
Attachments: 1. Location Map - Providence Road Sidewalk Project

Title

Providence Road Sidewalk Project

 

Action

Action                     

Award a contract in the amount of $456,982 to the lowest responsive bidder Sonny Development LLC for the Providence Road Sidewalk project.

 

Body

Staff Resource(s):

Mike Davis, Engineering and Property Management

Bette Frederick, Engineering and Property Management

 

Explanation

§                     This contract will construct 0.5 mile of sidewalk on the southwest side of Providence Road, filling in several gaps between Provence Village Lane and East Barden Road.

§                     The project supports the City’s Sidewalk Program to enhance connectivity, offer transportation choices, and improve pedestrian safety.

§                     This project is eligible for reimbursement of up to $750,000 from the North Carolina Department of Transportation through the Federal Congestion Mitigation and Air Quality Improvement Program for right-of-way, utility relocation, and construction.  The City is responsible for $325,000 as part of the grant agreement.  The total project cost is $1,075,000.

§                     On September 18, 2017 the City issued an Invitation to Bid; two bids were received from interested service providers.

§                     Sonny Development LLC was selected as the lowest responsive, responsible bidder.

§                     The project is anticipated to be completed by second quarter 2018.

 

Disadvantaged Business Enterprise (DBE) Opportunity

Established DBE Goal: 5.00%

Committed DBE Goal: 5.00%

Sonny Development met the established subcontracting goal, and has committed 5% ($22,849.10) of the total contract amount to the following certified firms:

§                     RRC Concrete (DBE, SBE) ($22,849.10) (concrete)

 

Fiscal Note

Funding:  Federal Congestion Mitigation and Air Quality Improvement Program and the General Community Investment Plan

 