Title: Faulconbridge Road Storm Drainage Improvement Project
Attachments: 1. Map - Faulconbridge Rd SDIP

Title

Faulconbridge Road Storm Drainage Improvement Project

 

Action

Action                     

A.                     Approve a contract in the amount of $917,855.25 to the lowest responsive, responsible bidder Onsite Development LLC for the Faulconbridge Road 5749 Storm Drainage Improvement Project, and

 

B.                     Authorize the City Manager to amend the contract consistent with the purpose for which the contract was approved.

 

Body

Staff Resource(s):

Angela Charles, Charlotte Water

Mike Davis, Storm Water Services

Logan Oliver, Storm Water Services

 

Explanation

§                     This project will replace and rehabilitate aging infrastructure across and adjacent to Falstaff Drive, Ganymede Place, and Faulconbridge Road in Council District 5.

§                     The work includes grading, storm drainage, curb and gutter, and asphalt paving.

§                     On May 4, 2026, the city issued an Invitation to Bid; three bids were received.

§                     Onsite Development LLC was selected as the lowest responsive, responsible bidder.

§                     The project is anticipated to be complete by the second quarter of 2027.

 

Charlotte Business INClusion

Established MBE Goal: 4.00%

Committed MBE Goal: 4.03%

Onsite Development, LLC exceeded the established contract goal and has committed 4.03% ($37,000) of the total contract amount to the following certified firm(s):

§                     Streeter Trucking Company (MBE, SBE) ($18,500) (hauling)

§                     Tony’s Trucking (MBE, SBE) ($18,500) (hauling)

 

Established WSBE Goal: 4.00%

Committed WSBE Goal: 4.03%

Onsite Development, LLC exceeded the established contract goal and has committed 4.03% ($37,000) of the total contract amount to the following certified firm(s):

§                     Armadillo Construction LLC (SBE) (37,000) (hauling)

 