Title
Cross Charlotte Trail Design Services
Action
Action:
A. Approve contract amendment #1 in the amount of $70,819 with Alta Planning & Design, Inc. for Cross Charlotte Trail Planning and Design Services, and
B. Authorize the City Manager to amend the contract consistent with the purpose for which the contract was approved.
Body
Staff Resource(s):
Phil Reiger, General Services
Kathleen Cishek, General Services
Keith Bryant, General Services
Explanation
§ The Cross Charlotte Trail (XCLT) is a joint project between the City of Charlotte and Mecklenburg County to create over 30 miles of continuous trail and greenway facilities.
§ Segment #8, currently in construction, is approximately 1.38 miles long and runs from Tryon Street to Orr Road in Council District 1.
§ On March 2, 2020, the city entered into a design services contract in the amount of $489,386 with Alta Planning & Design, Inc. for segment #8 of the XCLT.
§ Contract amendment #1 will include funding for value engineering and additional construction administration services.
§ The new total contract amount including contract amendment #1 is $560,205.
Charlotte Business INClusion
All additional work involved in this Amendment will be performed by Alta Planning & Design, Inc. and their existing subconsultant(s). Alta Planning & Design, Inc. has committed 10.25% ($57,425) of the total contract amount of the following certified firm(s):
§ The Dodd Studio, LLC, (SBE) ($15,165) (landscape architecture)
§ Stewart Engineering, Inc. (MBE) ($42,260) (geotechnical and erosion control services)
Fiscal Note
Funding: General Capital Investment Plan
Attachments
Attachment(s)
Map