Title
Bayswater Storm Drainage Improvement Project
Action
Action:
A. Approve contract amendment #2 for $750,000 to the contract with D&A Wolverine, PLLC for design and construction administration services for the Bayswater Storm Drainage Improvement Project, and
B. Authorize the City Manager to amend the contract consistent with the purpose for which the contract and this amendment were approved.
Body
Staff Resource(s):
Angela Charles, Charlotte Water
Mike Davis, Storm Water Services
Matthew Gustis, Storm Water Services
Explanation
* This project, with boundaries of Sharon Amity Road to the north, Campbell Creek to the south, Lawrence Orr Road to the east, and Vernedale Road to the west, will address aging infrastructure and reduce flooding in Council District 5.
* On February 28, 2022, following a competitive solicitation process, City Council approved a contract with D&A Wolverine, PLLC for $1,300,000 for the Bayswater Storm Drainage Improvement Project.
* Amendment #1 was to update the point of contact, correct the fee schedule, and hourly rates provided in the original agreement and did not impact the total value of the contract.
* Amendment #2 will provide design and construction administration services for the Bayswater Storm Drainage Improvement Project.
* Specific design and construction administration tasks include, but are not limited to:
* Design of repairs and/or improvements,
* Survey and utility locate services,
* Geotechnical subsurface investigations,
* Preparation of construction documents, and
* Construction administration.
* The new estimated value of the contract including this amendment is $2,050,000.
Charlotte Business INClusion
All additional work involved in this amendment will be performed by D & A Wolverine, PLLC and their existing subconsultant(s). D & A Wolverine, PLLC has committed 16.28% ($122,125) of the total contract amendment to the following certified firm(s):
* Survey & Mapping Control Inc. (SBE) ($122,125) (surveyi...