Airport Concourse A Ramp Expansion, Phase I Change Order
Action
Action:
Approve change order #1 for $706,817.65 to Flatiron Constructors Inc. - Blythe Development Company, A Joint Venture, for the construction of Concourse A Aircraft Ramp Expansion, Phase I.
Body
Staff Resource(s):
Brent Cagle, Aviation
Jack Christine, Aviation
Explanation
§ The Concourse A Aircraft Ramp Expansion project scope includes underground utility installation, jet fuel lines, grading, and the addition of concrete ramp pavement.
§ On May 9, 2016, City Council approved a contract in the amount of $39,799,138 to Flatiron Constructors Inc. - Blythe Development Company, A Joint Venture, for the construction of Concourse A Aircraft Ramp Expansion, Phase I Project.
§ This change order is needed to account for the increased expenses incurred during the relocation of a mid-field fueling station.
§ The new total value of the contract, including change order #1, is $40,505,955.65.
§ This activity is occurring on airport property, located in Council District 3.
Disadvantaged Business Enterprise
All additional work involved in this change order will be performed by Flatiron Constructors Inc. - Blythe Development Company, A Joint Venture, and their existing subcontractors.
Fiscal Note
Funding: Aviation Capital Investment Plan