Title
Lakeview Road Improvements Construction Change Order #1
Action
Action:
Approve change order #1 for $2,196,498.64 to Blythe Development, LLC for Lakeview Road Improvements project.
Body
Staff Resource(s):
Phil Reiger, General Services
Kathleen Cishek, General Services
Tonia Wimberly, General Services
Explanation
§ This project will widen Lakeview Road from Cushing Drive to Old Statesville Road (approximately 1.5 miles) and includes pavement upgrades, intersection modifications, additional through/turning lanes, drainage infrastructure, and pedestrian and bicycle facilities.
§ On November 8, 2021, Council approved the construction contract in the amount of $8,505,897.30 with Blythe Development Co.
§ The project timeline has been extended based on unplanned delays in the utility companies’ capacity to perform the relocations required for the project.
§ Change order #1 will include funds for the following major items which resulted from the 20-month utility delay:
- Material and labor costs associated with delays,
- Costs to extend subcontracting agreements, and
- Additional efforts to identify and clear utility conflicts.
§ The new total value of the contract is $10,702,395.94 and will be funded by the Federal Surface Transportation Block Grant Program and Direct Attributable and State Bonus Allocation.
§ The project is expected to be complete in the fourth quarter of 2026.
Disadvantaged Business Enterprise
Blythe Development Co. committed ($1,229,908) 11.49% of the total contract amount to the following certified firm:
§ RRC Concrete Inc. (DBE) ($1,229,908) (concrete)
Fiscal Note
Funding: General Capital Investment Plan
Attachments