Airport CLT Logistics Center Relocation
Action
Action:
Approve a contract in the amount of $3,446,501 to the lowest responsive bidder Keach Construction, Inc. for the CLT Logistics Center Relocation project.
Body
Staff Resource(s):
Haley Gentry, Aviation
Jack Christine, Aviation
Explanation
§ This project will include interior and exterior renovations at the Cargo 6 facility to accommodate the Aviation Logistics operation’s relocation from the CLT. This will allow for Logistics expansion as well as employee workspace needs at the CLT Center.
§ The project involves improvements to the fire protection system, employee workspace, offices, and restrooms, and replacing the roof at the Cargo 6 facility.
§ On January 26, 2026, the city issued an Invitation to Bid; four bids were received.
§ Keach Construction, Inc. was selected as the lowest responsive, responsible bidder.
§ The project is anticipated to be complete by the second quarter of fiscal year 2027.
Charlotte Business INClusion
Established MWSBE Goal: 10.00%
Committed MWSBE Goal: 31.94%
Keach Construction, Inc. exceeded the established subcontracting goal and has committed 31.94% ($1,100,882) of the total contract amount to the following certified firm(s):
§ Platinum Coating (WBE) ($12,564) (painting)
§ Stevens Interior (SBE) ($38,542) (drywall/act)
§ Tec Electric (MBE, SBE) ($1,049,776) (electrical)