Title: Airport CLT Logistics Center Relocation
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideoAudio
No records to display.

Title

Airport CLT Logistics Center Relocation

 

Action

Action                     

Approve a contract in the amount of $3,446,501 to the lowest responsive bidder Keach Construction, Inc. for the CLT Logistics Center Relocation project.

 

Body

Staff Resource(s):

Haley Gentry, Aviation

Jack Christine, Aviation

 

Explanation

§                     This project will include interior and exterior renovations at the Cargo 6 facility to accommodate the Aviation Logistics operation’s relocation from the CLT. This will allow for Logistics expansion as well as employee workspace needs at the CLT Center.

§                     The project involves improvements to the fire protection system, employee workspace, offices, and restrooms, and replacing the roof at the Cargo 6 facility.

§                     On January 26, 2026, the city issued an Invitation to Bid; four bids were received.

§                     Keach Construction, Inc. was selected as the lowest responsive, responsible bidder.

§                     The project is anticipated to be complete by the second quarter of fiscal year 2027.

 

Charlotte Business INClusion

Established MWSBE Goal: 10.00%

Committed MWSBE Goal: 31.94%

Keach Construction, Inc. exceeded the established subcontracting goal and has committed 31.94% ($1,100,882) of the total contract amount to the following certified firm(s):

§                     Platinum Coating (WBE) ($12,564) (painting)

§                     Stevens Interior (SBE) ($38,542) (drywall/act)

§                     Tec Electric (MBE, SBE) ($1,049,776) (electrical)

 

Fiscal Note

Funding: Aviation Capital Investment Plan