File #: 15-24936    Version: 1 Name:
Type: Consent Item Status: Approved
File created: 9/11/2025 In control: City Council Business Meeting
On agenda: 12/8/2025 Final action: 12/8/2025
Title: Airport Overlook Lighting Enhancements

Title

Airport Overlook Lighting Enhancements

 

Action

Action                     

Approve a contract in the amount of $546,059.36 to the lowest responsive bidder Brooks-Berry-Haynie & Associates, Inc. for the Overlook Lighting Enhancements project.

 

Body

Staff Resource(s):

Haley Gentry, Aviation

Jack Christine, Aviation

 

Explanation

§                     This project will provide for enhanced lighting at the Airport Overlook.

§                     Specific work includes replacing existing light poles, foundations, and bollards with fixtures that better illuminate the aircraft display, memorial, and playground.

§                     On August 25, 2025, the city issued an Invitation to Bid (ITB); one bid was received.

-                     NC General Statute Section 143-132 prohibits municipalities from awarding construction contracts over $500,000 without receiving at least three competitive bids from the initial advertisement of the contract. The city may subsequently award the contract even if readvertisements result in fewer than three competitive bids.

§                     On September 22, 2025, the city reissued the ITB; one bid was received.

§                     Brooks-Berry-Haynie & Associates, Inc. was selected as the lowest responsive, responsible bidder.

§                     The project is anticipated to be complete by the fourth quarter of fiscal year 2026.

 

Charlotte Business INClusion

Established MBE Goal: 6.00%

Committed MBE Goal: 17.88%

Brooks-Berry-Haynie & Associates, Inc. exceeded the established contract goal and has committed 17.88% ($97,635) of the base bid amount to the following certified firm(s):

§                     DMD Supply Services (MBE, SBE) ($97,635) (electrical)

 

Established SWBE Goal: 13.00%

Committed SWBE Goal: 13.00%

Brooks-Berry-Haynie & Associates, Inc. met the established subcontracting goal had has committed 13.00% ($70,988) of the base bid amount to the following certified firm(s):

§                     DMD Supply Services (MBE, SBE) ($70,988) (electrical)

 

Fiscal Note

Funding: Aviation Capital Investment Plan