Title: Construct Cross Charlotte Trail - Tryon Street to Orr Road
Attachments: 1. Map_Construct Cross Charlotte Trail - Tryon Street to Orr Road.pdf

Title

Construct Cross Charlotte Trail - Tryon Street to Orr Road

 

Action

Action                     

Approve a contract in the amount of $4,774,592.99 to the lowest responsive, responsible bidder J.D. Goodrum Co, Inc. for the Cross Charlotte Trail - Tryon Street to Orr Road project.

 

Body

Staff Resource(s):

Phil Reiger, General Services

Jennifer Smith, General Services

Keith Bryant, General Services

 

Explanation

§                     The Cross Charlotte Trail (XCLT) is a joint project between the City of Charlotte and Mecklenburg County to create over 30 miles of continuous trail and greenway facilities.

§                     This contract includes construction services for segment 8, North Tryon Street to Orr Road (1.38 miles plus 0.49 miles of neighborhood connector paths) of the XCLT trail through the Hidden Valley neighborhood in Council District 1.

§                     The work includes but is not limited to clearing, grading, retaining walls, boardwalks, storm drainage, accessibility ramps, sidewalk, landscaping, and asphalt and concrete pathways.

§                     On December 6, 2023, the city issued an Invitation to Bid; four bids were received.

§                     J.D. Goodrum Co, Inc. was selected as the lowest responsive, responsible bidder.

§                     The project is anticipated to be complete by third quarter 2026.

 

Charlotte Business INClusion

Established MWBE Goal:  8.00%

Committed MWBE Goal:  8.38%

J.D. Goodrum Co, Inc. exceeded the established contract goal and has committed 8.38% ($400,023) of the total contract amount to the following certified firms:

§                     On Time Construction, Inc. (WBE) ($220,000) (concrete)

§                     Affordable Source Trucking, LLC (MBE) ($75,000) (hauling)

§                     Maybury Fencing Inc. (WBE) ($54,000) (fence)

§                     Mid-Atlantic Erosion Control, Inc. (MBE) ($26,048) (erosion control, silt fence)

§                     Superior Seeding, Inc. (WBE) ($24,975) (matting, seeding)

 