Title
Central Business District Sanitary Sewer Construction Change Order
Action
Action:
Approve change order #2 to Sanders Utility Construction Co., Inc. for the Little Sugar Creek Tributary to Central Business District Sanitary Sewer project.
Body
Staff Resource(s):
Angela Charles, Charlotte Water
David Czerr, Charlotte Water
Carl Wilson, Charlotte Water
Explanation
§ This project involves the procurement, replacement, and construction of a sanitary sewer to serve a portion of the Central Business District (Council District 1).
§ This change order is estimated to be $703,000 for the repair of a recently installed 48-inch sanitary sewer main, which was damaged by a contractor working on an adjacent project.
§ The repairs are required now, and Charlotte Water will seek recovery of all costs associated with this repair.
§ On December 10, 2018, City Council approved a contract with Sanders Utility Construction Co., Inc. for Design-Build design services.
§ On February 10, 2020, City Council approved a guaranteed maximum price with Sanders Utility Construction Co., Inc. for Design-Build construction services of the Little Sugar Creek Tributary to Central Business District Sanitary Sewer project, which included installation of the 48-inch sanitary sewer, portions of which are still under construction.
§ The project is anticipated to be complete fourth quarter 2022.
§ The new total value of the contract, including this change order, is estimated to be $43,761,664.69.
Charlotte Business INClusion
All additional work involved in this Change Order will be performed by Sanders Utility Construction Co., Inc. and their existing subcontractors (Part D: Section 6 of the Charlotte Business INClusion Policy).
Fiscal Note
Funding: Charlotte Water Capital Investment Plan