Title
Airport Federal Inspection Station Facility and Concourse D Renovations Guaranteed Maximum Price Amendment
Action
Action:
Approve Guaranteed Maximum Price Amendment #3 for $7,077,675.04 to the contract with Messer Construction Co. for the Construction Manager at Risk services for the Federal Inspection Station Facility and Concourse D Renovations project.
Body
Staff Resource(s):
Haley Gentry, Aviation
Jack Christine, Aviation
Explanation
* The Federal Inspection Station Facility (FIS) was built in 1990 and expanded in 2000. Increases in international traffic have necessitated the renovation and expansion of the FIS facility and Concourse D.
* The project will provide for the 115,000-square-foot renovation of the FIS facility on the lower level of Concourse D and 99,000-square-foot renovation of the ticket level of Concourse D.
* Complex vertical construction and renovations, such as this project, are well suited to the Construction Manager at Risk (CMAR) delivery method.
* CMAR projects often include multiple planned GMP Amendments to address long lead time for materials and equipment, phased project delivery to maintain operations in an around-the-clock facility, or modified design dictated by timed facility closing(s) or demolition.
* On July 10, 2023, following a competitive solicitation process, City Council approved a CMAR contract with Messer Construction Co. in the amount of $3,509,420.89 to procure the major mechanical, electrical, and plumbing equipment for the project.
* This project has included two previous GMP amendments, both of which were routine and ensured the project remains aligned with current code requirements and operational needs.
* GMP Amendment #1 in the amount of $39,255,742.27 was to incorporate the GMP for the construction of the Concourse D ticket level renovation. This work included new flooring, lighting, and gate podiums, public address system upgrades, charging stations for hold room seating, and renovating the r...
Click here for full text