Title
Collective Storm Drainage Improvement Project - Series N
Action
Action:
A. Approve a contract in the amount of $928,390.40 to the lowest responsive bidder OnSite Development, LLC for the Collective Storm Drainage Improvement Project - Series N, and
B. Authorize the City Manager to amend the contract consistent with the purpose for which the contract was approved.
Body
Staff Resource(s):
Angela Charles, Charlotte Water
Mike Davis, Storm Water Services
Logan Oliver, Storm Water Services
Explanation
§ The contract is part of an ongoing program to provide repairs and/or improvements to storm
drainage systems.
§ The contract will address storm drainage systems at:
- 6101 Hickory Forest Drive (Council District 7), and
- 6114 Hickory Forest Drive (Council District 7).
§ On October 1, 2024, the city issued an Invitation to Bid; nine bids were received.
§ OnSite Development, LLC was selected as the lowest responsive, responsible bidder.
§ The project is anticipated to be complete by first quarter 2026.
Charlotte Business INClusion
Established MBE Goal: 7.00%
Committed MBE Goal: 7.00%
OnSite Development, LLC met the established contract goal and has committed 7.00% ($64,988) of the total contract amount to the following certified firm(s):
§ LJR Concrete, LLC (MBE, SBE) ($30,000) (concrete)
§ Streeter Trucking Company (MBE, SBE) ($17,494) (hauling)
§ Tony’s Trucking (MBE, SBE) ($17,494) (hauling)
Established WBE Goal: 4.00%
Committed WBE Goal: 4.00%
OnSite Development, LLC met the established contract goal and has committed 4.00% ($37,136) of the total contract amount to the following certified firm(s):
§ Keys Trucking, LLC (WBE, SBE) ($37,136) (hauling)
Fiscal Note
Funding: Stormwater Capital Investment Plan