Title
Stowe Regional Water Resource Recovery Facility Construction Phase 2
Action
Action:
Approve a guaranteed maximum price of $57,985,658 to Crowder/Garney JV for Design-Build construction services for the Stowe Regional Water Resource Recovery Facility project.
Body
Staff Resource(s):
Angela Charles, Charlotte Water
David Czerr, Charlotte Water
Ron Hargrove, Charlotte Water
Explanation
§ Crowder/Garney JV has developed a guaranteed maximum price (GMP) for major treatment process components to be constructed as part of the Stowe Regional Water Resource Recovery Facility (SRWRRF) project (adjacent to Council Districts 2 and 3).
§ The SRWRRF will treat wastewater flows from the existing Long Creek basin and flows from the cities of Mount Holly and Belmont.
§ On April 27, 2020, and January 25, 2021, City Council approved contracts totaling $31,416,107 with Crowder/Garney JV for design services.
§ On February 14, 2022, May 31, 2022, September 12, 2022, and December 12, 2022, City Council approved GMPs totaling $153,695,529 with Crowder/Garney JV for the procurement of equipment, construction infrastructure, and associated site work.
§ City Council will receive a future request for the approval of an additional construction phase.
§ The SRWRRF is estimated to be in operation by second quarter 2026.
Charlotte Business INClusion
The city negotiates subcontracting participation for Design-Build contracts after the firm is selected and scopes of work are defined for design and construction services. Crowder/Garney JV has committed $6,410,849 or approximately 11.06% of the contract for construction services, design build design services or approved tasks, etc. to the following certified firms (Part G: Section 2.4 of the Charlotte Business INClusion Policy):
§ McFarland Building Group LLC (MBE) ($2,412,000) (maintenance building package)
§ Pedulla Trucking Excavating & Paving, Inc. (WBE) ($1,513,358) (sitework)
§ CITI, LLC (MBE) ($828,689) (instrumentation and controls)
§ HG Global Services, Inc. (SBE) ($565,000) (miscellaneous metals)
§ Presa Construction, LLC (MBE, SBE) ($423,300) (roofing)
§ Diamond Trucking of NC, Inc. (MBE, SBE) ($178,299) (trucking and aggregate hauling)
§ Kingdom Trucking, LLC (MBE, SBE) ($178,299) (trucking and aggregate hauling)
§ Redstone Materials, Inc. (MBE, SBE) ($178,299) (trucking and aggregate hauling)
§ Diva Dumps, LLC dba Diva Dumps (MBE, SBE) ($77,520) (toilets and dumpsters)
§ Harrisburg Security, Inc. (SBE) ($41,866) (site security)
§ The Survey Company (SBE) ($9,185) (surveying)
§ Gentry Cleaners, Inc. (MBE, SBE) ($5,034) (janitorial services)
Fiscal Note
Funding: Charlotte Water Capital Investment Plan