File #: 15-7241    Version: 1 Name:
Type: Consent Item Status: Approved
File created: 12/27/2017 In control: City Council Business Meeting
On agenda: 2/26/2018 Final action: 2/26/2018
Title: Davidson Water Main Construction and Construction Management Contracts
Attachments: 1. Davidson WTM RCA Map

Title

Davidson Water Main Construction and Construction Management Contracts

 

Action

Action                     

A.                     Award a contract in the amount of $4,305,037.00 to the lowest responsive bidder Propst Construction Company for the Davidson Water Transmission Main project, and

 

B.                     Approve a professional services contract for $299,900.00 with Willis Engineers, Inc. for construction administration services.

 

Body

Staff Resource(s):

Angela Lee, Charlotte Water

Ron Hargrove, Charlotte Water

Carl Wilson, Charlotte Water

 

Explanation

§                     Charlotte Water serves more than 950,000 customers in the City of Charlotte and greater Mecklenburg County -- including the towns of Cornelius, Davidson, Huntersville, Matthews, Mint Hill, and Pineville.​​ ​​​​

§                     The Charlotte Water Master Plan identified a new 24-inch water transmission main is needed in the Towns of Cornelius and Davidson to improve water service, alleviate low pressures, and augment fire flows in the area.

§                     The Davidson Water Transmission Main project begins at Catawba Avenue in Cornelius and extends along South Street to Concord Road in Davidson. This project will consist of 11,500 feet of water main ranging from six through 24 inches.

§                     The project is anticipated to be complete by the first quarter of 2019.

§                     A future phase of the Davidson Water Transmission Main is anticipated to be constructed from downtown Davidson north to the Iredell County line. This design contract is anticipated to be submitted for Council consideration in the fourth quarter of 2018.

 

Action A - Construction Contract

§                     On January 12, 2018, Charlotte Water issued an Invitation to Bid for the Davidson Water Transmission Main; three bids were received from interested service providers.

§                     Propst Construction Company was selected as the lowest responsive, responsible bidder.

 

Action B - Construction Administration Services Contract

§                     The contract provides engineering services for the construction phase and includes inspection services as well as construction materials testing.

§                     On March 16, 2012, Charlotte Water issued a Request for Qualifications for design and construction phase services for the project; five responses were due from interested service providers.

§                     Willis Engineers, Inc. was selected as the best qualified firm to meet the service needs on the basis of demonstrated competence and qualifications.

§                     The contract for design services with Willis Engineers, Inc. was $246,716.

 

Charlotte Business INClusion

Action A - Construction Contract

Established MSBE Goal: 10.00%
Committed MSBE Goal: 10.00%

Propst Construction Company met the established subcontracting goal and has committed 10.00% ($430,508.50) of the total contract amount to the following certified firm(s) (Part B: Section 3 of the Charlotte Business INClusion Policy):

§                     D’s Trucking Service Inc. (SBE, WBE) ($155,201.00) (hauling)

§                     B & B Concrete Construction of Charlotte, Inc. (SBE) ($141,418.00) (curb and gutter)

§                     Trull Contracting, LLC (SBE, WBE) ($101,675.00) (sidewalk/driveway and asphalt paving)

§                     P&TL, Inc. (SBE) ($32,214.50) (erosion control and landscaping)

 

Action B - Construction Administration Services Contract

The City negotiates subcontracting participation after the proposal selection process (Part C: Section 2.1(h) of the Charlotte Business INClusion Policy). Willis Engineers, Inc. has committed 1.8% ($5,500) of the total contract amount to the following certified firm:

§                     Survey & Mapping Control, Inc. (SBE) ($5,500) (as-built survey)

 

Willis Engineers, Inc. is a City certified SBE.

 

Fiscal Note

Funding:  Charlotte Water Community Investment Plan

 

Attachments

Attachment(s)

Map

Bid Results