Title: Parkwood Phase 1 - Brevard Street Culvert
Attachments: 1. Location Map - Parkwood Phase 1 - Brevard Street Culvert

Title

Parkwood Phase 1 - Brevard Street Culvert

 

Action

Action:                       

Award a contract in the amount of $1,578,906.60 to the lowest responsive bidder Sealand Contractors Corp. for the Parkwood Phase 1 - Brevard Street Culvert project.

 

Body

Staff Resource(s):

Matthew Gustis, Engineering & Property Management

 

Explanation

§                     The Parkwood Phase 1 - Brevard Street Culvert project will reduce flooding of streets, properties, and structures.

§                     The project area is located in the Upper Little Sugar Creek watershed and situated on North Brevard Street near the Belmont Avenue intersection.

§                     The work will include:

-                     Storm drainage,

-                     Curb and gutter,

-                     Driveways,

-                     Asphalt pavement and replacement,

-                     Traffic control, and

-                     Water and sanitary sewer installation.

§                     On August 15, 2016, the City issued an Invitation to Bid for the Parkwood Phase 1 - Brevard Street Culvert Project; four bids were received from interested service providers.

§                     Sealand Contractors Corp. was selected as the lowest responsive, responsible bidder.

§                     The project is anticipated to be complete by third quarter of 2017.


Background

§                     The Brevard Street culvert work was initially included within the Parkwood Phase 1 Storm Drainage Improvement project.

§                     The work on Brevard Street was removed from the project in order to coordinate with redevelopment plans in the Highland Mills area.

 

Charlotte Business INClusion

Established SBE Goal: 16.00%
Committed SBE Goal: 16.00%
Sealand Contractors Corp., met the established SBE subcontracting goal, and has committed 16.00% ($252,625) of the total contract amount to the following certified SBE firms (Part B: Section 3 of the Charlotte Business INClusion Policy):

                     On Time Construction, Inc. (SBE, MBE) ($166,540) (concrete)

                     D’s Trucking Service Inc. (SBE) ($43,042.50) (hauling)

                     R C Hauling, Inc. (SBE) ($43,042.50) (hauling)


Established MBE Goal: 6.00%
Committed MBE Goal: 10.55%
Sealand Contractors Corp. exceeded the established subcontracting goal, and has committed 10.55% ($166,540) of the total contract amount to the following certified MBE firms (Part B: Section 3 of the Charlotte Business INClusion Policy):

                     On Time Construction, Inc. (SBE, MBE) ($166,540) (concrete)

 

Fiscal Note

Funding:  Storm Water Community Investment Plan

 