Title: Engineering Services for Water and Sanitary Sewer Relocations and Improvements

Title

Engineering Services for Water and Sanitary Sewer Relocations and Improvements

 

Action

Action:

A.                     Approve unit prices contracts with the following companies for engineering and sanitary sewer relocations and improvement for an initial term of three years:

-                     Colliers Engineering & Design, CT., P.C.,

-                     Hinde Engineering, Inc. (SBE),

-                     Kimley-Horn and Associates,

-                     Stantec Consulting Services, Inc., and

 

B.                     Authorize the City Manager to renew the contract for up to two, one-year terms with possible price adjustments and to amend the contract consistent with the purpose for which the contract was approved.

 

Body

Staff Resource(s):

Angela Charles, Charlotte Water

David Czerr, Charlotte Water

Carl Wilson, Charlotte Water

 

Explanation

§                     These contracts are needed to provide design and construction administration services to utility coordination on state, city, town, and Mecklenburg County projects related to Charlotte Water’s existing and proposed infrastructure along with miscellaneous water and wastewater improvements.

§                     On April 24, 2024, the city issued a Request for Qualifications (RFQ); eight responses were received.

§                     The companies selected are the best qualified firms to meet the city’s needs on the basis of demonstrated competence and qualification of professional services in response to the RFQ requirements.

§                     The vendor for specific projects/tasks will be chosen based on the vendors availability, current projects distribution, and proximity of the assigned project to other projects.

§                     Annual expenditures are estimated to be $1,920,000.

 

Charlotte Business INClusion

The city negotiates contract participation after the proposal selection process. Each of the Primes has committed 10% of the total contract amount to the following certified firm(s):

Colliers Engineering & Design

§                     DiCon Consulting, PC (SBE) (engineering support)

§                     Hinde Engineering, Inc. (SBE) (engineering support)

§                     RDL Private Utility Locating, LLC (MBE) (engineering support)

§                     Stewart Engineering, Inc. (MBE) (engineering support)

Hinde Engineering, Inc. (SBE)

§                     DiCon Consulting, PC (SBE) (construction observation services)

Kimley-Horn and Associates

§                     Capstone Civil Engineering, Inc. (MBE, SBE) (geotechnical engineering)

§                     Center Line Locating, LLC (WBE, SBE) (underground utility locating, soft digs, cctv)

§                     DiCon Consulting, PC (SBE) (construction administration, construction observation and inspection)

§                     James Mauney & Associates, PA (SBE) (surveying and mapping services)

§                     RDL Private Utility Locating, LLC (MBE) (subsurface utility exploration)

§                     Stewart Engineering, Inc. (MBE) (surveying and subsurface utility exploration)

Stantec Consulting Services, Inc.

§                     DiCon Consulting, PC (SBE) (inspection, utility construction observation)

 

Fiscal Note

Funding: Charlotte Water Capital Investment Plan