Title
Storm Drainage Improvement Projects Series B
Action
Action:
Award a contract in the amount of $1,537,822.00 to the lowest responsive bidder Onsite Development, LLC for the Storm Drainage Improvement Projects Series B.
Body
Staff Resource(s):
Mike Davis, Engineering and Property Management
Bong Vang, Engineering and Property Management
Explanation
§ This contract is part of an ongoing program to provide repairs and improvements to existing storm drainage systems and construction of new storm drainage systems.
- Each request is investigated and prioritized based on the severity of potential public/private property flooding and/or property damage.
- The necessary repairs for each project are designed and a work order prepared.
§ Contract B will address failing storm drainage systems in the following locations:
- 4600 The Plaza (Council District 1),
- 333 East Trade Street (Council District 1),
- 5743 Barrington Drive (Council District 5),
- 3320 Fortis Lane (Council District 5),
- 216 Burleigh Street (Council District 6),
- 620 Edgemont Road (Council District 6), and
- 2130 Valencia Terrace (Council District 6).
§ Work will also include grading, drainage, sidewalks, curb and gutter, and water mains and services to existing infrastructure that increases safety and provides maintenance upgrades to roads.
§ On April 18, 2018, the City issued an Invitation to Bid for Collective Storm Drainage Improvement Projects Series B; four bids were received from interested service providers.
§ Onsite Development, LLC was selected as the lowest responsive, responsible bidder.
§ These projects are anticipated to be complete by end of first quarter 2019.
Charlotte Business INClusion
Established SBE Goal: 17.00%
Committed SBE Goal: 25.17
OnSite Development exceeded the established subcontracting goal, and has committed 25.17% ($387,000) of the total contract amount to the following certified firms (Part B: Section 3 of the Charlotte Business INClusion Policy):
§ RRC Concrete (SBE, MBE) ($75,000) (concrete)
§ L Carranza Trucking (SBE) ($46,400) (hauling)
§ JV Trucking (SBE) ($46,400) (hauling)
§ Affordable Source Trucking (SBE, MBE) ($46,400) (hauling)
§ Streeter Trucking (SBE, MBE) ($46,400) (hauling)
§ MTS Trucking (SBE, MBE) ($46,400) (hauling)
§ AMP (SBE) ($40,000) (materials)
§ Axiom Foundations (SBE) (40,000) (foundation)
Established MBE Goal: 8.00%
Committed MBE Goal: 13.93%
OnSite Development exceeded the established subcontracting goal, and has committed 13.93% ($214,200) of the total contract amount to the following certified firms (Part B: Section 3 of the Charlotte Business INClusion Policy):
§ RRC Concrete (SBE, MBE) ($75,000) (concrete)
§ Affordable Source Trucking (SBE, MBE) ($46,400) (hauling)
§ Streeter Trucking (SBE, MBE) ($46,400) (hauling)
§ MTS Trucking (SBE, MBE) ($46,400) (hauling)
Fiscal Note
Funding: Stormwater Community Investment Plan
Attachments
Attachment(s)
Map